Per AES Indiana, Google will cover 100% of its incremental energy and new infrastructure costs for a 390 MW data center in Monrovia under a roughly $1.3 billion power plan the Indiana Utility Regulatory Commission approved unanimously, the first case under the state's 2025 large-load cost law. In North Carolina, a Duke Energy settlement backed by Amazon, Google, Meta, and Microsoft would set a 75% minimum monthly billing demand, upfront payment for dedicated facilities, and security for network upgrades on new loads as small as 50 MW, with a utilities commission decision expected by mid-November. Who pays for the megawatts is turning into a site-selection screen for AI campuses.